An automation concurrently support 50 steps but I would suggest limiting yourself to 25. You can have those first 24 steps create 24 children and populate a field with child number in each step from 1 to 24.
You can then look up the number of children that were required from, the parent down to the children and have Step 25 delete any excess children where their child # was higher than what was required.​
------------------------------