Show how many days for timeline report
Hi All, I'm creating a timeline report to track the process of recruitment from advertisement until contracted. Below is the result
It's possible to show how many days is needed from s...
- 6 years agoYou can make a formula duration field and write it like this
[contracted date] - [referee checking date]
then add the new field to the report
------------------------------