SyaefulBahri3
6 years agoQrew Trainee
Show how many days for timeline report
Hi All,
I'm creating a timeline report to track the process of recruitment from advertisement until contracted. Below is the result
It's possible to show how many days is needed from start to end? in my case is from referee checking date until contracted date. For example, 30 days needed for the process, etc.
Many thanks
------------------------------
Syaeful Bahri
------------------------------
I'm creating a timeline report to track the process of recruitment from advertisement until contracted. Below is the result
It's possible to show how many days is needed from start to end? in my case is from referee checking date until contracted date. For example, 30 days needed for the process, etc.
Many thanks
------------------------------
Syaeful Bahri
------------------------------
- You can make a formula duration field and write it like this
[contracted date] - [referee checking date]
then add the new field to the report
------------------------------
Everett Patterson
------------------------------